695 metres.
One decisive drive.

A landmark large-diameter microtunnel delivered beneath one of Dubai’s most critical transport corridors.

Al Khail Road microtunnel cutterhead at breakthrough in Dubai
Drive length695 m
Internal diameter3,500 mm
Outer diameter4,200 mm
MethodMicrotunnelling
Intermediate jacking4 IJS
Guidance systemVMT Gyro

Controlled delivery at scale

The 695 m drive used four intermediate jacking stations to distribute thrust along the 4,200 mm OD pipe string.

Alignment control was provided by a VMT Gyro guidance system throughout the long-distance drive. The combination of planned IJS operation, guidance control, slurry management and coordinated site execution supported the successful crossing beneath Al Khail Road.